OFFSHORE
ENERGY

OFFSHORE ENERGY
References
Equinor
REFERENCES
Prosjekt Equinor – Lining 3“-4“-8“
Job Executed for costumer Aker solutions
EXECUTION OF LEAK WATER LINE AT MONGSTAD
3.2 km total pipe have been lined where the Leak
water was from Johan Sverdrup field.
.jpg)
.jpg)
.jpg)
Equinor
REFERENCES
FLOTATION TANK ON SFA AND GFA
Equinor – Flotasjons tanker
Job Executed for costume Equinor
Total lamination of flotation tanker with extended life. Build in a 7-layered system including 2 layered polyester cloth 2.5mm.



Equinor
REFERENCES
LINING "3-4"-8"
Equinor – lining
Job Executed for costume Aker Solution
Caisson 36,dimentions 26’’/DN660, pipe in Carbon steel + 2 x 3.5 m spools with 12” connections Produced water.
Constant temperature 80˚C Peak temperature 99˚C



EQUINOR
Gullfaks A LQ
DRAINPIPE REHABILITATION

Moreld Apply
Gullfaks C 2023
Equinor – Open drain lining rehabilitation
Job Executed for costumeEquinor
Rehabilitation of drainage system from level 3 to level 9 (L11-L12-L13), including the open drain, kitchen, laundry room, and cabin annex.
Full lining of the entire pipe system in the living quarters. Pipe dimensions range from Dn.70 to DN150, using Loro-x pipes. The inner lining of corroded pipes was carried out without disrupting living quarters, with no need for disassembly or posing any risk to health, safety, and environment. The work was done as a closed system, ensuring a safe and efficient process for sewage rehabilitation.

Moreld Apply – Innerlining of collector pipe for torch
to liquid separator
INNERLINING OF
COLLECTOR PIPE
We conducted an inner lining of the collector pipe for torch to liquid separator in LT torch 43-VD02. The project involved epoxy lining of a fully welded 12˝ collector pipe, including branches through the fire wall.
The pipe dimensions, tank, pressure, and temperature specifications are as follows: 12" -6" Pipeclass AC17 sch20.
Job Description: Our scope of work included cleaning and applying a DN300 Epoxy liner over a 15m length. Additionally, we performed up milling of the 8˝ and 6˝ branches and installed 2 top hats to complete the project.



Equinor
Sleipner R
Equinor – Rehabilitation of open drain system from upper mezz deck to under Main-deck
OPEN DRAIN SYSTEM
56_SLR/2023
We completed a full epoxy lining from stake/blind flanges and all drain-boxes, extending from the beginning to the end above the sea. The pipe dimensions, tank, pressure, and temperature specifications are as follows: DN 250/DN 200/DN 150/DN 100 carbon steel.
Job Description: Our scope of work involved installing an inside epoxy liner in the open drainpipes leading out to sea, including support pipes/reinforcement from the top deck on Sleipner R platform. Before applying the epoxy liner, we thoroughly cleaned the inside corrosion throughout the entire pipe system. Additionally, we installed Y-liners in other branches.